Yulong copper mine phase III expansion gets green light
2025-06-26 14:05:28 [Print]
On June 23, Tibet Yulong Copper Co
The open-pit expansion includes a new 11-million-tonne-per-year concentrator, expansion of hydrometallurgical refining capacity from 300,000 tonnes to 1 million tonnes per year, and supporting infrastructure such as a new tailings storage facility. The upgraded mine, which mainly produces copper concentrate, molybdenum concentrate, and refined copper, will have a projected service life of 23 years, with an estimated total investment of RMB4 . 8 billion (USD669 million).
By the end of 2024, Yulong copper mine had 830 million tonnes of ore resources at 0.6% Cu on average, and produced 159,000 tonnes of mined copper that year . Once Phase III is completed, the annual mined copper output is expected to rise to 180,000-200,000 tonnes, further strengthening the company's production capacity.
. , Ltd . , a subsidiary of Western Mining, received approval from the Development and Reform Commission of Tibet Autonomous Region for its Phase III expansion project at the Yulong copper mine . The project will boost production capacity from 19 . 89 million to 30 million tonnes per year.The open-pit expansion includes a new 11-million-tonne-per-year concentrator, expansion of hydrometallurgical refining capacity from 300,000 tonnes to 1 million tonnes per year, and supporting infrastructure such as a new tailings storage facility. The upgraded mine, which mainly produces copper concentrate, molybdenum concentrate, and refined copper, will have a projected service life of 23 years, with an estimated total investment of RMB4 . 8 billion (USD669 million).
By the end of 2024, Yulong copper mine had 830 million tonnes of ore resources at 0.6% Cu on average, and produced 159,000 tonnes of mined copper that year . Once Phase III is completed, the annual mined copper output is expected to rise to 180,000-200,000 tonnes, further strengthening the company's production capacity.