Hainan Mining's lithium hydroxide project finishes hot commissioning
2025-03-03 15:08:06 [Print]
Hainan Mining Co
The project, constructed and operated by Hainan Xingzhihai New Materials Co., Ltd . , a majority-owned subsidiary of Hainan Mining, commenced construction in late 2022.
Following the completion of main construction and the partial trial production, the project is expected to go into formal operation and see finished products in April 2025.
. , Ltd . announced successful hot commissioning of a 20,000tpa battery grade lithium hydroxide project located at Yangpu New Materials Park in Danzhou, Hainan. The project, constructed and operated by Hainan Xingzhihai New Materials Co., Ltd . , a majority-owned subsidiary of Hainan Mining, commenced construction in late 2022.
Following the completion of main construction and the partial trial production, the project is expected to go into formal operation and see finished products in April 2025.