• Silicon Metal 5-5-3 Delivered Europedown(-50)  05-12|Silicon Metal 4-4-1 Delivered Europedown(-50)  05-12|Tungsten Oxide WO3 99.95%min FOB Chinaup(10)  05-12|Tungsten Scrap CNC Cutting Blades 70%min Ex-VAT Delivered Chinaup(5)  05-12|Antimony Trioxide 99.5%min In warehouse Rotterdamup(1.3)  05-12|Tungsten Scrap Drills 70%min Ex-VAT Delivered Chinaup(5)  05-12|Sodium Pyroantimonate 58.4% Delivered Chinadown(-3000)  05-12|Tungsten Scrap Anvil 90%min Ex-VAT Delivered Chinaup(5)  05-12|Silico-chrome Si 42%min, Cr 30%min EXW Chinadown(-200)  05-12|Manganese Ore 38%min FOB S.A. up(0.07)  05-12|Ferro-tungsten 70%min EXW Chinaup(5000)  05-12|Antimony Ingot 99.65%min In port Indiaup(100)  05-12|Silicon Powder 99%min Delivered Chinadown(-200)  05-12|Ferro-silicon 75%min In warehouse Pittsburghup(0.02)  05-12
  • Taseko announces 2024 production results and expects production increase at Gibraltar mine in 2025

    2025-01-10 14:24:43   [Print]
    BEIJING (Asian Metal) 10 Jan 25 – Taseko Mines Limited (TSX: TKO; NYSE American: TGB; LSE: TKO) ("Taseko" or the "Company") announces 2024 production from its 100% owned Gibraltar copper mine.Asian Metal Copyright" "The silver stream amendment follows our acquisition of the remaining 12.Asian Metal Copyright Copper and molybdenum production for the year was 106 million pounds and 1.Asian Metal Copyright In late December, the Company closed a transaction with Osisko Gold Royalties to amend the Gibraltar silver steam agreement, increasing the attributable silver percentage from 87.Asian Metal Copyright4 million pounds, respectively.Asian Metal Copyright Taseko owns and operates the Gibraltar copper-molybdenum mine, located in south-central British Columbia.Asian Metal Copyright Sales volumes for the year were 108 million pounds of copper and 1.Asian Metal Copyright4 million lb.Asian Metal Copyright4 million pounds of molybdenum.

    In late December, the Company closed a transaction with Osisko Gold Royalties to amend the Gibraltar silver steam agreement, increasing the attributable silver percentage from 87.5% to 100%.Asian Metal Copyright5% to 100%.Asian Metal Copyright In exchange, Taseko has received an additional cash payment of US$12.Asian Metal Copyright Copper and molybdenum production for the year was 106 million pounds and 1.Asian Metal Copyright7 million.

    Stuart McDonald, President & CEO of Taseko, commented, "Since completion of the planned major maintenance activities in July, milling operations at Gibraltar have been running smoothly. Mill throughput averaged over 89,000 tons per day in the fourth quarter, 5% over design capacity, resulting in copper production of 29 million pounds for the period.Asian Metal Copyright Taseko owns and operates the Gibraltar copper-molybdenum mine, located in south-central British Columbia.Asian Metal Copyright Looking ahead to 2025, increased mill availability is expected to result in annual copper production of 120 to 130 million pounds, a significant increase over last year, although production is expected to be weighted to the second half of the year."

    "The silver stream amendment follows our acquisition of the remaining 12.5% Gibraltar joint venture interest last March, and the additional cash proceeds further strengthen our balance sheet during this period of construction spending at Florence Copper," concluded Mr.Asian Metal Copyright4 million lb.Asian Metal Copyright McDonald.

    Taseko Mines (TSX: TKO) says increased mill availability at its Gibraltar copper mine will mean annual production of 120-130 million lb., representing a significant production increase over 2024.Asian Metal Copyright "Since completion of the planned major maintenance activities in July, milling operations at Gibraltar have been running smoothly," CEO Stuart McDonald said in a news release.Asian Metal Copyright However, the company stressed this increased production will occur in the latter part of the year.

    Taseko owns and operates the Gibraltar copper-molybdenum mine, located in south-central British Columbia. It is the second largest open pit copper mine in Canada and the largest employer in the Cariboo region.

    Taseko acquired Gibraltar in 1999 and restarted operations in 2004. It now considers the mine to be its foundational asset.Asian Metal Copyright, representing a significant production increase over 2024.Asian Metal Copyright Analysts have stated Gibraltar will be able to support copper and molybdenum production until at least 2044.

    On Thursday, the company released its 2024 production numbers for Gibraltar. Company officials stated copper and molybdenum production for the year was 106 million lb.Asian Metal Copyright" In late December, Taseko closed a transaction with Osisko Gold Royalties to amend the Gibraltar silver steam agreement, increasing the attributable silver percentage from 87.Asian Metal Copyright and 1.Asian Metal CopyrightBEIJING Asian Metal 10 Jan 25 – Taseko Mines Limited TSX: TKO; NYSE American: TGB; LSE: TKO "Taseko" or the "Company" announces 2024 production from its 100% owned Gibraltar copper mine.Asian Metal Copyright4 million lb.Asian Metal Copyright" In late December, Taseko closed a transaction with Osisko Gold Royalties to amend the Gibraltar silver steam agreement, increasing the attributable silver percentage from 87.Asian Metal Copyright, respectively, while sales volumes for the year were 108 million lb.Asian Metal Copyright" "The silver stream amendment follows our acquisition of the remaining 12.Asian Metal Copyright of copper and 1.Asian Metal Copyright Mill throughput averaged over 89,000 tons per day in the fourth quarter, 5% over design capacity, resulting in copper production of 29 million pounds for the period.Asian Metal Copyright4 million lb.Asian Metal Copyright4 million pounds, respectively.Asian Metal Copyright of molybdenum.

    "Since completion of the planned major maintenance activities in July, milling operations at Gibraltar have been running smoothly," CEO Stuart McDonald said in a news release. "Mill throughput averaged over 89,000 tons per day in the fourth quarter, 5% over design capacity, resulting in copper production of 29 million lb.Asian Metal Copyright Taseko Mines TSX: TKO says increased mill availability at its Gibraltar copper mine will mean annual production of 120-130 million lb.Asian Metal Copyright for the period."

    In late December, Taseko closed a transaction with Osisko Gold Royalties to amend the Gibraltar silver steam agreement, increasing the attributable silver percentage from 87.5% to 100%.Asian Metal Copyright It now considers the mine to be its foundational asset.Asian Metal Copyright In exchange, Taseko has received an additional cash payment of $12.Asian Metal Copyright McDonald.Asian Metal Copyright7 million.

    The silver stream amendment follows Taseko's acquisition of the remaining 12.5% Gibraltar joint venture interest last March.

    According to McDonald, the additional cash proceeds will help further strengthen the company's balance sheet during a period of construction at its Florence Copper project in Arizona.

    .Asian Metal Copyright of copper and 1Asian Metal Copyright
    Copper Conc. 20%min Delivered China
    Unit:RMB/mt Cu
    Copper Conc. 20%min Delivered China RMB/mt Cu
    China copper concentrate producers' sales to production ratio statistics by province by month
    Unit: %
      Copyright © Asian Metal Ltd All rights reserved.